Question 102 - Kevin is a senior developer that has recently joined an existing Scrum Team. The existing team members are unable to get along with Kevin and conclude that he is not a culture fit. If necessary, who is responsible for removing the new team member, and why?

  • The HR department, as they are responsible for the hiring process.

  • The Development Team is responsible, and may request help from the Scrum Master.

  • The Product Owner because he/she is responsible for managing the team.

  • The Scrum Master because he/she is responsible for removing Impediments.

Overall explanation

  • The ones closest to the problem are the best ones to understand and solve the problems.