Question 6 - Who creates a Product Backlog item's estimate?
-
The Product Owner with input from the Development Team
-
The most senior people in the organization, including architects and subject matter
-
The Development Team after clarifying requirements with the Product Owner
-
The Scrum Master
-
The Development Team alone
Overall explanation
- The Development Team is responsible for all estimates.
- The Product Owner may influence the Development Team by helping it understand and select trade-offs, but the people who will perform the work make the final estimate.
Question 8 - Who is responsible for estimating the Product Backlog items?
-
The Development Team by themselves.
-
The Product Owner.
-
The Technical Architect.
-
The Scrum Master.
-
The Development Team after clarifying the requirements with the Product Owner.
Overall explanation
- The ones doing the work are the best ones to create the estimations.
Question 31 - Which concept illustrates that, as a forecast lengthens, the level of unknowns also increase? (choose the best answer)
-
Empirical process control
-
The "Iron Triangle"
-
The "cone of uncertainty"
-
Software Product Life Cycle
Overall explanation
- The Cone of Uncertainty describes the evolution of the amount of best case uncertainty during a project.
- At the beginning of a project, comparatively little is known about the product or work results, and so estimates are subject to large uncertainty.
- As more research and development is done, more information is learned about the project, and the uncertainty then tends to decrease.