Question 47 - For the Product Backlog Refinement act, the Scrum Team needs to define a recurring pre-set time every week outside the current working hours of the Development Team.
-
False
-
True
Overall explanation
- Product Backlog refinement is the act of adding detail, estimates, and order to items in the Product Backlog.
- This is an ongoing process in which the Product Owner and the Development Team collaborate on the details of Product Backlog items.
- During Product Backlog refinement, items are reviewed and revised.
- The Scrum Team decides how and when refinement is done.
- Refinement usually consumes no more than 10% of the capacity of the Development Team.
Question 104 - The Product Owner can invite the stakeholders to the Backlog Refinement sessions
-
Yes
-
No
Overall explanation
- Stakeholders can be invited to Backlog Refinement sessions as needed.