Question 92 -Which answer best describes the topics covered in Sprint Planning?
-
How conditions have changed and how the Product backlog should evolve
-
What can be done and how to do it
-
What went wrong in the last Sprint and what to do differently this Sprint
-
Who is on the team and what team member roles will be
-
What to do and who will do it
Overall explanation
- The work to be performed in the Sprint is planned at the Sprint Planning.
- This plan is created by the collaborative work of the entire Scrum Team.
- Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint.
- For shorter Sprints, the event is usually shorter.
- The Scrum Master ensures that the event takes place and that attendants understand its purpose.
- The Scrum Master teaches the Scrum Team to keep it within the time-box.
- Sprint Planning answers the following:
- What can be delivered in the Increment resulting from the upcoming Sprint?
- How will the work needed to deliver the Increment be achieved?
Question 116 - What prerequisites must be met before a Sprint Planning can start? (choose the best answer)
-
The preparedness of the Product Owner.
-
Approval from the steering committee.
-
Availability of key Scrum Team members.
-
A fully refined Product Backlog.
-
There are no such prerequisites.
-
User Stories that conform with the Definition of Ready.
Overall explanation
- Scrum events should be held at the same time each Sprint.
- This helps with consistency, making improvements to the process, and reducing waste.
- In an event that a Scrum event cannot begin at the Scrum Team's designated time, they will need to inspect and adapt the event itself in order to maximize the effectiveness of the event.
- Delaying events is a short-term solution and results in reducing the team's opportunities to improve.
Question 119 - Select the correct statement. Before the Sprint Planning
-
None of the above
-
The Product Backlog Items must be refined with complete acceptance criteria before they are chosen for Sprint
-
The Development Team must have a definition of “Done” formally approved by the Product Owner
-
Completed user stories must be posted on the Scrum Board
Overall explanation
- The Definition of “Done” doesn’t need the Product Owner’s approval.
- A Scrum Board, User Stories and Acceptance Criteria are good practices but not mandatory parts of Scrum (they are not even mentioned in the Scrum Guide).